Actuals — plan vs reported
The Actuals tab is where the plan meets reality. Everywhere else in Resourcing you are looking forward — who should do the work. Actuals looks back: for each person, week by week, it puts the hours they were planned for next to the hours they actually reported in Time Tracking, and shows the gap between the two.
That gap — the variance — is the number the tab exists to produce. It answers the one question a plan on its own never can: did it survive contact with reality?
How to read a cell
Each cell is a small bullet chart. The filled bar is the hours the person actually reported that week; the line drawn across it is the plan. Reading the two together tells you the story at a glance:
- Fill past the line — they reported more than the plan. Someone quietly doing more than the plan admits is exactly the thing that stays invisible until a project is late.
- Fill short of the line — they reported less than the plan, whether because the work slipped or because the time was never logged.
- Fill level with the line — plan and reality agree. This is what healthy looks like.
Everything is measured against that person's own contracted week. Someone on a 0.6 FTE contract who reports their full part-time week reads as fully delivered against a full plan — not as a shortfall. The share is always relative to the hours they are contracted for.
Two empty cells look similar but mean different things:
- An empty fill inside a plan line — the person was booked, but nothing was reported against that week. The loudest signal on the screen, and it costs no extra reading.
- A cell with no line and no fill — the person had no active contract that week, so there is nothing to measure. This reads as no contract, not as a miss.
The variance column
The right-hand column totals the period into one figure per person: the reported hours against the planned hours, as a percentage and in hours. It is coloured so the outliers find you — over the plan, under the plan, or holding exactly. "Plan held" is the quiet, healthy case.
Where the hours went
A person reporting under their plan raises an obvious question: where did the rest of the time go? Expanding a row answers it in place. The breakdown splits the reported hours by project, largest first, and ends with Unreported — the capacity the plan expected that has no hours logged against it.
Unreported is deliberately its own line, with its own hatched marker. It is a gap in the data, not proof that nothing happened — and it is never quietly folded into another category. Seeing it is the point: it is usually a prompt to go and log the missing time, not evidence of idle capacity.
Where this sits
Actuals reads two things Flowtly already holds — the bookings that make up the plan, and the time tracked against projects — and puts them in one place so nobody has to do the subtraction in their head. It changes nothing: it reports. Booking and confirming still happen on Projects; logging time still happens in Time Tracking.