Budget realization

Flowtly Editorial Team3 min

Budget realization is a sub-tab of a project's Financials, beside Initial budget, Plan vs Actual, Team costs over time and Related costs. It answers one question: for each line you planned, how much has been committed in contracts, and how much of that has been invoiced?

It needs an initial budget to compare against. Until the project has one, the tab says so and points you at the Initial budget sub-tab.

How the table is organised

The table has one row per tag. Tags are what tie a budget line to the contracts and invoices that spend against it, so the tags on your initial budget are the rows you see here.

Each row shows:

Column What it means
Tag The budget tag the row is about.
Budget realization Two bars. The lighter one is the share of the plan your contracts already cover; the darker one is the share that has been invoiced.
Planned (net) What the initial budget set aside for this tag.
Contracted (net) The net value of the project's contracts allocated to this tag.
Invoiced (net) What has actually been invoiced against it.

An orange tail on the bar marks an overrun — contracted value has passed the plan. It is worth checking whether the contract is wrong or the budget needs updating.

A Total row sums the rows on screen. Use the search field to narrow to one tag, and select a row to expand the contracts behind it without leaving the tab. A tag showing zero contracts is in the plan but has nothing linked to it yet.

Contracts without a tag

The table shows budgeted tags only. A contract that carries no tag has no row to belong to, so it is left out of the table and out of the Total.

When that happens the tab says so, above the table: how many contracts were left out and what they are worth together. A project whose contracts are all untagged would otherwise read exactly like a project with no contracts at all — every figure zero, no row, nothing on screen to distinguish the two.

The contracts themselves are not hidden anywhere else. To see them, open Related costs, which lists what has actually hit the project regardless of tagging.

To bring an untagged contract into this table, give it a tag that the initial budget uses. Tagging it against a tag the budget does not carry still leaves it out, because there is no planned line for it to be compared with.

Example use cases

  • A project manager checks halfway through a build which budget lines are already fully committed in contracts, and which still have room.
  • A controller spots an orange overrun tail on one tag, opens the row, and finds the contract that pushed it past the plan.
  • Someone reading a project whose figures are all zero sees the notice above the table, learns that eight contracts are untagged, and tags them so the comparison becomes meaningful.
  • A finance lead reconciles contracted against invoiced value per tag to see how much of the committed spend has actually been billed.

Connection map

Refers toDerived fromPart ofPlanned vs actual
Documented hereDocumented elsewhere
budget covers project. invoice billed from project. project is of type project-type. project identified by project-reference. project staffed by person. project-rate rates person. project-rate applies on project. time-entry tracked against project. task belongs to project. project-folder groups project. project linked to budget. project-template creates project. project-phase is a child project of project. project needs role. booking planned vs actual time-entry.coversbilled fromis of typeidentified bystaffed byratesapplies ontracked againstbelongs togroupslinked tocreatesis a child project ofneedsplanned vs actualBBudget — The financial envelope an engagement is measured against — what was planned, versus what has actually been spent.BudgetPProject — The core organizational unit for a business initiative, client engagement or internal work. Everything tracked — time, cost, invoicing, profitability — hangs off one.ProjectIInvoice — A sales document issued to a client: line items, dates, tax. It is created, reviewed, previewed and then sent.InvoicePProject type — Fixed-price, Time & Material, Non-billable or Internal. It decides how the project's tracking and reporting behave.Project typePProject reference — An optional key a project carries so systems outside Flowtly can name it. Unique within the organisation, and never reused once it has been given to a project.Project referencePPerson — An employee. The central record the rest of the workforce data hangs off — profile, documents, leave, benefits, rates.PersonMMember rate — A team member's billing or cost rate on a project. Rates are per member, so the same person can cost differently on two projects.Member rateTTime entry — What actually happened — work time logged against a project.Time entryTTask — A unit of work inside a project.TaskPProject folder — A grouping of projects, for organisations running more than a handful.Project folderPProject template — A reusable blueprint for a project: its phases, task lists and tasks, with timings held as day offsets rather than dates. It carries no client, no team and nothing financial.Project templatePPhase — A stage a project runs through. A phase is itself a child project, so everything true of a project is true of a phase.PhaseRRole — One job to be done on a project. It may be open, partly filled, filled or over-filled, and it exists whether or not anyone is booked on it.RoleBBooking — One person committed to one role for a stretch of weeks, at a percentage of their time. A booking is a plan, not a record of work done.Booking