Forecast at completion (FAC)

General

The projected final cost of a project, calculated from actual cost incurred to date plus the expected cost of the work still remaining. Because it is an estimate, a forecast at completion should be presented as a prediction, not a booked figure.

Why it matters

A project budget says what the work was expected to cost; the forecast at completion says what it will actually cost, given everything that has happened so far. Reviewing it regularly turns an overrun into a decision taken in month two instead of a surprise in month six.

Formula

FAC = actual cost to date + estimate to complete (ETC)

Worked example

A project budgeted at €100,000 has spent €60,000, and the team estimates another €55,000 of work to finish. The forecast at completion is €115,000: an expected overrun of €15,000 against budget.