Budget variance

General

The difference between planned and actual figures, used to analyse performance. A favourable variance means spending was below budget or revenue exceeded expectations; an unfavorable one signals the need for corrective action.

Budget variance

Why it matters

A variance is only useful while there is still time to act on it. Comparing budget with actuals every month, or every week on projects, shows whether an overrun comes from price, volume or timing, and whether the forecast for the rest of the year has to change.

Formula

Budget variance = actual − budget; variance % = (actual − budget) ÷ budget × 100%

Worked example

The marketing budget for Q2 was 50 000 € and actual spend was 56 000 €. The variance is 6 000 €, or 12% over budget. On a cost line that is unfavourable; on a revenue line the same positive variance would be favourable.